Welcome to Karnataka Regional Youth Convention

CONVENTION HALL & STAGE COMMITTEE

KRYC
Regional Youth Convention 2019 (RYC)

(24.10.2019-27.10.2019)

CONVENTION HALL & STAGE COMMITTEE

CONVENER: Denis

CORDINATOR:

Person In Charge Requirement Volunteers Required
Bangalore DEXCO

Cyril Prabhu (Abide)

10 walkie talkie
Garlands
Bouquets
Shawls
Coordinate with exhibition committee
Coordinate with light & sound
MCs to be prepared and informed well in advance
Coordinate with VIP committee for guest list
All required materials to arrive one day before at back stage
Coordinate with decoration committee for stage decoration

35


ACTIVITY DAYS/WEEKS REQUIRED START DATE END DATE PERSON RESPONSIBLE

1. Study Venue and Facilities

2. Assess Requirements:
Panda I & Stage areas
Furniture stage /ground
Road Arches (???)

3. Design Layout

4. Identify / List Tent Houses

5. Call for Quotations

6. Scrutinize quotations / Finalize

7. Prepare Budget of the Committee

8. Present Budget to LOC and get approval from ICYM Regional Office



STAGE PROGRAM COMMITTEE

KRYC
Regional Youth Convention 2019 (RYC)

(24.10.2019-27.10.2019)

STAGE PROGRAM COMMITTEE

CONVENER: Cleeta

CORDINATOR:

Person In Charge Requirement Volunteers Required
Gulburga DEXCO)

programme
Requirement on the stage
Light and sound
Time allotment

15


ACTIVITY DAYS/WEEKS REQUIRED START DATE END DATE PERSON RESPONSIBLE

1. Gather information from Theme Committee

2. Brainstorm on general directions on: Souvenir Mementoes

3. Letters to DYDs-for ideas / suggestions

4. Souvenir: Finalize Advt. Rates / Tariffs Advt. Forms / Request Letters Distribution of Forms Reports / Articles / Regional Report / Advertisement / List of LOC Members, Regional Office Members, etc.

5. Cover Design / Convention Logo

6. Maintain Daily Accounts of Incoming Advt., Donations, Other receipts and payments.

7. Assess requirement of Paper for Souvenir: Quotations from printers / memento mfrs. Evaluate Quotations and finalize

8. Prepare Budget for Souvenir Committee

9. Present Budget to LOC and get approval from ICYM Regional Office

10. Distribute / post Souvenirs



Note:

When planning the activities - 1. Please consider the activities of your own committee in co-relation with the other committees. 2. The impact of these dates on the target Starts date of the Convention. 3. Plan backwards and ensure that the entire task of the Committee is completed latest by 30.09.2019 so that the Convention takes off smoothly on 24.10.2019. 4. If tasks are pending or incomplete inform the Core group well in time.